Bellevue Retrofit and Full House Remodel
This Bellevue, WA home underwent a full retrofit and interior transformation focused on layout improvements, long-term performance, and a clean modern finish. The scope included a full kitchen rebuild, renovated bathrooms, new flooring and paint throughout, and major system upgrades. Key retrofit work included ceiling vaulting, skylight integration, and structural beam and post work to support the updated layout and open feel.
Existing Conditions
The home had dated finishes, limited lighting, and an older interior layout that did not match how the homeowners wanted to use the space. Multiple areas required deeper updates once walls and ceilings were opened. The original configuration also limited openness in the main living zones, and several systems were due for modernization.
Scope of Work
Retrofit and structural work including ceiling vaulting and structural reinforcement, skylight work, and framing adjustments to support the updated layout.
Full kitchen rebuild including new cabinet layout, waterfall island execution, backsplash tile, updated lighting, and reworked plumbing and gas lines for appliances and features such as a pot filler.
Primary and guest bathroom renovations including demolition, updated layouts where required, waterproofing systems, tile installation, shower and tub work, new fixtures, and radiant floor heating.
Whole-home interior improvements including drywall replacement and finish preparation, interior paint, doors and trim package, flooring installation through main areas, and detailed finish transitions.
Mechanical and system modernization including electrical upgrades, plumbing rough-in updates, ventilation routing, and HVAC improvements and relocation as needed.
Exterior and roof-related repair scope connected to the retrofit work, including targeted repairs, sealing, and paint where required.
Challenges
Ceiling and structural retrofit: vaulting, skylight integration, and beam and post work required careful sequencing so the final geometry, load paths, and finish lines stayed clean.
Whole-home coordination: a multi-room remodel required tight trade coordination and correct rough-in placement so cabinetry, tile, and finish elevations aligned without rework.
High-finish execution: features like a waterfall island, modern cabinetry, large-format tile, and clean trim lines demand precision and tight tolerances.
Comfort and performance upgrades: radiant floor heating and improved system routing needed to be planned early so transitions and floor heights stayed correct.
Solutions
Retrofit-first sequencing: framing and structural work were completed early so electrical, drywall, and finishes could land accurately and consistently.
Light and volume improvements: the vaulted ceiling and skylight brought more natural light and a more open feel to the main living areas.
MEP integration with finish planning: electrical, plumbing, gas, and ventilation were coordinated with cabinetry and tile layouts for a clean final result.
Detail-focused finishes: tile edges, transitions, trim alignment, and cabinetry detailing were handled with a consistent approach across the entire home.
Work Performed by NBE LLC
Demolition and preparation for retrofit work, including removal of drywall and insulation where required.
Framing modifications including opening adjustments, ceiling vaulting work, and structural beam and post framing.
Skylight work coordination and finish integration.
Kitchen rebuild including cabinet installation, island framing support as required, backsplash tile, plumbing and appliance coordination, and lighting updates.
Bathroom renovations including shower conversion and waterproofing, tile systems, tub and plumbing work, radiant floor heating installation, and fixture installation.
Whole-home finishes including drywall installation and finish prep, interior painting, doors, trim, and flooring installation.
Systems coordination including electrical and plumbing rough-in updates, ventilation routing, and HVAC improvements as needed.
Exterior and roof-related repairs tied to the retrofit work, plus sealing and finishing where required.
Result
The home was transformed into a brighter, open, modern living space with improved flow and a consistent finish level throughout. The vaulted ceiling and skylight added volume and natural light, structural beam and post work supported the updated layout, and high-end features like the waterfall island and radiant floor heating elevated both comfort and design. The project delivered not only a new look, but also deeper retrofit upgrades behind the walls for long-term value.